Bren Shop home/sport court new build
(recently completed)
(recently completed)
This project is a 2600 sq ft home, 1030 sq ft sport court and 420 sq ft garage square foot build.
Construction began September 2025 and was completed July 2026
Construction began September 2025 and was completed July 2026
Excavation - Phase 1, Footings - Phase 2
Framing - Phase 3
Plumbing/Ductwork - Phase 4
Concrete - Phase 5
Trusses/Roofing - Phase 6
Underlayment - Phase 7
Siding/Soffits/Doors/Windows - Phase 8, 9, 10, 11
Finish Work/Kitchen - Phase 12